FAQ
This depends on the load being supported and whether the unit connects across site supporting multiple loads. For dedicated loads and locations single units are often utilised, however we would recommend for single units there is a connection for routine load bank testing and a temporary hire unit should one be required. For centralised standby generators these are normally configured in an N+ configuration, to ensure the most critical loads can be supported in the event of servicing or failure of one of the generator units.